Notting Hill Genesis · Case 201913098 · 4 December 2020
Notting Hill Genesis — case 201913098
The landlord apologised for delays in complaint handling, accepted it had not always followed its ASB policy, offered £50 compensation, and installed a secure gate. Following mediation, the resident confirmed the complaint was resolved satisfactorily, leading to a finding of resolved with intervention.
Orders and recommendations
- Apology
Apologised for delay in responding to the complaint
- Compensation
£50 compensation offered for failures
- Take specific action
Installation of secure gate outside the resident's front door and replacement of the main block gate
Compensation ordered
| Reason | Amount |
|---|---|
| Compensation for failures in responding to ASB reports and complaint handling delay | £50 |
| Total | £50 |
Findings by complaint head
Summarised automatically from the decision below. The Ombudsman's decision text is the authoritative record.
-
Response to ASB reports
Mediation / settlementFollowing Ombudsman intervention, the landlord apologised for complaint handling delay, accepted it had not always responded to ASB reports per its policy, offered £50 compensation, and completed installation of a secure gate. The resident confirmed the complaint was resolved satisfactorily.
The full determination
REPORT COMPLAINT 201913098 Notting Hill Genesis 4 December 2020 Our approach Under our early resolution process, the Ombudsman works with the resident and landlord to explore the issues in dispute, identify the matters that remain outstanding and assist in reaching an agreed settlement. The complaint The complaint is about the landlord’s response to the Resident’s reports of antisocial behaviour (ASB). Determination (decision) In accordance with paragraph 55 (c) of the Housing Ombudsman Scheme, the landlord has made an offer of redress to the complainant which, in the Ombudsman’s opinion, resolves the complaint satisfactorily.
How the complaint was resolved On 8 April 2020 the landlord issued its final complaint response to the Resident and said that: “It apologised for the delay in responding to their complaint; It had acted on their suggestion that a secure gate be installed outside their front door; It accepted that it had not always responded to their ASB reports in accordance with its ASB policy; It offered compensation of £50.” On 19 June 2020, having brought their complaint to this Service, the Resident agreed to engage in our mediation process and said that, as an outcome from the complaint, they wanted the landlord to upgrade or, replace the main gate to their block, so that it locked, in order to improve security.
The landlord also agreed to engage in our mediation process and said that it already had plans in place to replace the gate at the block but that due to restrictions in place as a result of the ongoing Covid-19 pandemic, it was not sure when it would be able to complete works. This Service discussed the landlord’s response with the Resident, and they responded and said that they would only consider their complaint resolved once the works to replace the gate had been completed.
The landlord subsequently advised that the gate had been ordered for installation and the works were completed during the week commencing 2 November 2020. The Ombudsman contacted the Resident to enquire whether the complaint had been resolved to their satisfaction, and they confirmed in their email of 23 November 2020, that it had. Paragraph 55 (c) of the Housing Ombudsman Scheme states that: “At any time, the Ombudsman may determine the investigation of a complaint immediately if satisfied that the member has made an offer of redress following the Ombudsman’s intervention which, in the Ombudsman’s opinion, resolves the complaint satisfactorily.
This will result in a finding of ‘resolved with intervention’.” For the reasons detailed above, I am satisfied, following the intervention of this Service, that the landlord has completed actions which resolve the complaint satisfactorily.
This is a structured summary of a published determination. The official decision is the authoritative record. Contains public sector information licensed under the Open Government Licence v3.0.