Notting Hill Genesis · Case 202321386 · 29 April 2026
Notting Hill Genesis — case 202321386
The Ombudsman found maladministration in the landlord's decision not to pay the resident compensation for inconvenience caused by cladding repair works, as it failed to justify treating her differently from other residents for the period she lived in the block. It also found maladministration in complaint handling because the stage 2 response was sent 83 working days after escalation, over 60 days outside the required timeframe. The landlord was ordered to apologise, pay £350 compensation, and reconsider its compensation decision.
Orders and recommendations
- ApologyWithin 4 weeks
The landlord must apologise in writing to the resident for the failures identified, ensuring the apology is specific, meaningful and empathetic with due regard to the apologies guidance.
- CompensationWithin 4 weeks
Pay the resident £350: £200 for the decision not to pay compensation for inconvenience caused by repair works and £150 for complaint handling. The landlord may deduct any payments already paid.
- Take specific actionWithin 4 weeks
Reconsider its decision not to pay the resident compensation for the relevant period, considering all relevant factors, and send the resident and the Ombudsman evidence of its decision. If it decides to pay increased compensation, it must do so by the due date.
Compensation ordered
| Reason | Amount |
|---|---|
| Decision not to pay compensation for inconvenience caused by repair works | £200 |
| Complaint handling failure | £150 |
| Total | £350 |
Findings by complaint head
-
Decision not to pay the resident compensation
MaladministrationThe landlord failed to justify its decision to treat the resident differently from other residents. The resident was impacted in exactly the same way as other residents between November 2021 and May 2022, and the landlord did not explain why she should not benefit from the compensation scheme for the period she lived in the block, nor why it offered a 10% goodwill rent reduction rather than the 15% offered to existing residents.
-
Complaint handling
MaladministrationThe landlord's stage 2 complaint response was sent 83 working days after the escalation request, over 60 days outside the required timeframe, with no explanation, apology or compensation offered.
The full determination
Decision Case ID 202321386 Decision type Investigation Landlord Notting Hill Genesis Landlord type Housing Association Occupancy Secure Tenancy Date 29 April 2026 Background The resident was the landlord’s tenant in a block (the block) which required repairs including replacement cladding. These works began in November 2021. The resident moved out in May 2022. The works were initially expected to take about 1 year. However, in late 2022, the landlord discovered that they would take another 3 years.
In February 2023, it decided to offer current residents of the block compensation. The resident did not qualify and complained. What the complaint is about The complaint is about the landlord’s: Decision not to pay the resident compensation for inconvenience caused by repair works. Complaint handling. Our decision (determination) There was maladministration in the landlord’s: Decision not to pay the resident compensation for inconvenience caused by repair works. Complaint handling.
We have made orders for the landlord to put things right. Summary of reasons Decision not to pay the resident compensation The landlord failed to justify its decision not to pay the resident the compensation on offer to residents for the period when she lived in the block. Complaint handling The landlord’s stage 2 complaint response was sent 83 working days after the escalation request which was outside the requirements of the Code. Putting things right Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right.
We have the discretion to make recommendations in all other cases within our jurisdiction. Orders Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set. Order What the landlord must do Due date 1 Apology order The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure: The apology is specific to the failures identified in this decision, meaningful and empathetic.
It has due regard to our apologies guidance. No later than 27 May 2026 2 Compensation order The landlord must pay the resident £350 made up as follows: £200 for the decision not to pay the resident compensation for inconvenience caused by repair works £150 for complaint handling. This must be paid directly to the resident and the landlord must provide documentary evidence of payment by the due date. The landlord may deduct any payments it has already paid from the total figure.
No later than 27 May 2026 3 Specific action order The landlord must reconsider its decision not to pay the resident compensation for the relevant period. It must consider all relevant factors and send the resident and the Ombudsman evidence of its decision by the due date. If it decides to pay the resident increased compensation, it must do so by the due date. No later than 27 May 2026 Our investigation The complaint procedure Date What happened 20 September 2023 We passed the resident’s complaint to the landlord.
She complained that she should have been awarded compensation for the impact of building works on her while she was a resident of the block. 28 September 2023 The landlord provided its stage 1 response. It said: It would only pay compensation to current residents. It decided to pay compensation in February 2023, because it had discovered that the works would last an additional 3 years. She was not a resident at the time the decision was made so could not benefit from it as she had not been impacted in the same way as current residents.
However, as a goodwill gesture, it would pay the resident 10% of her rent for a period of 25 weeks during which she had scaffolding outside her flat. This amounted to £345.85 8 October 2023 The resident asked to escalate her complaint to stage 2 of the landlord’s complaint process. She asked it to explain why she did not qualify. She said the entirety of her decade long stay at the block had been horrible and the cladding had been there throughout. 10 February 2024 The landlord provided its stage 2 response in which it repeated its reasoning from the stage 1 response.
11 March 2024 The resident asked the Ombudsman to investigate. She said the compensation offered by the landlord had been insufficient. What we found and why The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
Complaint The decision not to pay the resident compensation Finding Maladministration The resident lived at the block for over a decade. In 2020, scaffolding was erected after problems with its cladding were discovered. Works began to replace cladding in 2021. The works were expected to take about 2 years. The landlord offered some residents the chance to move and the resident took advantage of this offer, moving out in May 2022. The resident says that, while she was living at the property, the landlord had already made it clear that it intended to offer compensation to residents and that the landlord’s staff told her to attend residents’ meetings to ensure that she received it.
We have no reason to doubt her word, but, as we have seen no evidence to support this claim, we are unable to make a determination on this point. In 2022, the initial, exploratory phase of works found that the repairs required were more extensive than previously thought. They would take approximately 2 years longer than expected. In February 2023, the landlord’s board decided that it would: Offer all current residents the chance to move to alternative accommodation, put them in Band A for housing allocations and pay £3,000 towards moving costs.
Pay residents who stayed 20% of their rent for each week that the works went on. Pay an extra 15% of rent to those whose flats were surrounded by scaffolding for each week that the works went on. Offer counselling, pay legal fees and offer financial advice to all residents. Not offer compensation to former residents. When she found out about the compensation offer, the resident asked to be compensated, alongside current residents, for the period when she had lived in the block and had been affected by the works; a period of 25 weeks.
In its stage 1 and 2 responses sent in September 2023 and February 2024, the landlord said that she did not qualify for the compensation offered in February 2023 because: It had only decided to pay compensation after it had discovered that the works would take longer than previously thought. This decision had been made in February 2023 after she moved out. She would not be affected in the same way as current residents. However, it offered her a 10% “goodwill gesture” rent reduction for the period between the date that the scaffolding was erected outside her flat, in November 2023 and the day she left in May 2023, a period of 25 weeks.
In our view, the landlord failed to justify its decision to treat the resident differently from other residents. In its complaint response, iIt said that she was not affected “in the same way” as residents who continued to live in the block because she moved out in May 2022. But, clearly, between November 2021 and May 2022, she was impacted in exactly the same way as other residents. The inconvenience they all suffered at that time was unaffected by the subsequent discovery that the works would last for a further 3 years.
The landlord says that the decision to offer compensation was made after the resident moved out. Nonetheless, the decision covers a period during which she lived there. The compensation was to be paid from the beginning of the works until the end. The landlord has not explained why she should not benefit for the period when she lived in the block. We would also note that the landlord failed to explain why it offered the resident a “goodwill gesture” of a 10% rent reduction in recognition of the impact of having scaffolding outside her property for 25 weeks rather than the 15% it offered existing residents under its compensation scheme.
In our view, therefore, the landlord’s decisionamounted to maladministration because it failed to explain its decision adequately and the explanation it gave did not provide a proper justification for its decision. Thispotentially had a considerable financial impact on the resident. Had it awarded her 35% of her rent, as it did to those who remained, over the 25-week period rather than 10%, it would have offered her £1,211 rather than £345. We have ordered the landlord to reconsider this decision and to write to the resident and to us explaining its reasoning for any decision.
We have also ordered it to pay a sum, £200, in recognition of the inconvenience and distress its failure caused in line with our guidance on compensation. Complaint The handling of the complaint Finding Choose an item. The landlord’s published complaints policy complies with the terms of the Code in respect of timescales which says that landlords should provide a complaint response within 10 working days of a complaint. It must provide a stage 2 response within working 20 days of a request for a stage 2 review.
It could ask for a maximum of 20 extra working days to deal with complex complaints which require further investigation. It must acknowledge complaints and escalation requests in writing within 5 working days. In this case, we asked the landlord to respond to the resident’s complaint on 20 September 2023. It provided a complaint response on 28 September 2023, well within its policy timeframe. The resident asked to escalate her complaint on 8 October 2023. It provided its stage 2 complaint response on 6 February 2024.
This was 83 days later and over 60 days outside the required timeframe. The landlord provided no explanation for this delay. Nor did it apologise or pay compensation. For that reason, we have made a finding that there was maladministration. We have ordered the landlord to pay the resident £150 in compensation and apologise which is in line with our guidance on compensation and remedies. Learning We encourage landlords to use the learning resources available on our website. The centre for learning has a library of resources on topics such as complaint handling, repairs, knowledge and information management and Awaab’s Law.
Please visit https://www.housing-ombudsman.org.uk/centre-for-learning Knowledge information management (record keeping) The failure to respond to the resident’s complaint at stage 2 within its required timeframe may be evidence of poor record keeping. The landlord should consider the recommendations in the Ombudsman’s spotlight report on Knowledge and Information Management for accurate record keeping. Communication The landlord maintained regular communications with residents through meetings and emails which was appropriate and good service.