Clarion Housing Association Limited · Case 202348146 · 19 May 2026
Clarion Housing Association Limited — case 202348146
The Ombudsman did not investigate the landlord's handling of the Section 20 process for major works, as this is better dealt with by the First Tier Tribunal. It found service failure in the landlord's response to the resident's concerns about the major works and its communication, due to unclear, general responses and poor record keeping. It found reasonable redress in the complaint handling, where the landlord acknowledged a delay and offered proportionate compensation. The landlord was ordered to apologise and pay £450 compensation.
Orders and recommendations
- ApologyWithin 4 weeks
The landlord must apologise in writing to the resident for the failures identified in this report, ensuring the apology is specific, meaningful and empathetic with due regard to the apologies guidance.
- CompensationWithin 4 weeks
The landlord must pay the resident £450, previously offered in its stage 2 response for the delays in responding and the failures it identified with its stage 1 response. The landlord may deduct any payments already made.
Compensation ordered
| Reason | Amount |
|---|---|
| Compensation previously offered in stage 2 response for delays in responding and failures identified with stage 1 response | £450 |
| Total | £450 |
Findings by complaint head
-
Landlord's handling of the Section 20 process for its major works
Outside jurisdictionNot investigated as the Section 20 dispute is better dealt with by the First Tier Tribunal, which is better placed to examine Section 20 disputes and make legally binding orders.
-
Landlord's response to the resident's concerns about the major works and its communication
Service failureThe landlord did not provide clear or consistent responses, and gaps in its records meant it could not fully address the resident's concerns, leading to confusion and frustration. Responses were general, not tailored to the resident's concerns, and inconsistent notice dates reduced trust.
-
The handling of the complaint
Reasonable redressThe landlord acknowledged the delay at stage 2 and made an offer of compensation which was proportionate to the failings identified. The landlord met its policy timescales throughout.
The full determination
Decision Case ID 202348146 Decision type Investigation Landlord Clarion Housing Association Limited Landlord type Housing Association Occupancy Leaseholder Date 19 May 2026 Background The resident raised concerns to the landlord (the freeholder) about how it handled and communicated 2 sets of major works (the internal and external works and the fire remedial works). At the time of both major works, the property was occupied by his tenant. He said the landlord did not provide clear responses to his queries, he did not receive key information, particularly the Section 20 notices, and as a result he was unable to take part in the process.
The resident no longer owns the property. What the complaint is about The landlord’s handling of the Section 20 process for its major works. The landlord’s response to the resident’s concerns about the major works and its communication. The associated complaint. Our decision (determination) We have not investigated the landlord’s handling of the Section 20 process for its major works. There was service failure by the landlord in its response to the resident’s concerns about the major works and its communication.
There was reasonable redress by the landlord in the associated complaint. We have made orders for the landlord to put things right. Summary of reasons The landlord’s handling of the Section 20 process for its major works We do not investigate complaints where it would be quicker, fairer, more reasonable, or more effective to seek a remedy through the court, tribunal or other procedure. In this case, the complaint about the Section 20 process of the major works is better dealt with by the First Tier Tribunal (FTT).
This is because the FTT are better placed to examine Section 20 disputes in detail and make legally binding orders on the parties involved. Therefore, it is more appropriate for the resident seek the outcomes he wants with that tribunal. For these reasons, we have decided not to investigate this complaint point. The landlord’s response to the resident’s concerns about the major works and its communication The landlord did not provide clear or consistent responses, and gaps in its records meant it could not fully address the resident’s concerns, leading to confusion and frustration.
The complaint handling The complaint response was delayed at stage 2. However, the landlord acknowledged the delay and made an offer of compensation which we consider proportionate to the failings identified by our investigation. Putting things right Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction. Orders Landlords must comply with our orders in the manner and timescales we specify.
The landlord must provide documentary evidence of compliance with our orders by the due date set. Order What the landlord must do Due date 1 Apology order The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure: the apology is specific to the failures identified in this decision, meaningful and empathetic it has due regard to our apologies guidance No later than 17 June 2026 2 Compensation order The landlord must pay the resident £450 made up as follows: £450 previously offered in its stage 2 response for the delays in responding and the failures it identified with its stage 1 response.
The landlord must provide documentary evidence of payment by the due date. This must be paid directly to the resident by the due date. The landlord may deduct from the total figure any payments it has already paid. No later than 17 June 2026 Recommendations Our recommendations are not binding, and a landlord may decide not to follow them. Our recommendations We recommend that the landlord pays the £50 it offered for complaint handling. If it has not already done so. Our finding of reasonable redress was based on this compensation.
We recommend the landlord provides the resident with a copy of the Section 20 notice for the 2020/2021 major works, if this is still available. Our investigation The complaint procedure Date What happened 13 January 2024 The resident contacted the landlord to raise a complaint due to this lack of communication. In summary, he said: the landlord did not respond to his previous letters the landlord sent letters to the wrong address the landlord did not follow the Section 20 process the landlord did not hold discussions with leaseholders and did not answer his earlier questions he did not receive: consultation on the planned works any communication for over 2 years an estimate of costs or a final cost estimate notification of when the works would start a full account summary.
19 January 2024 The landlord acknowledged the residents complaint. 2 February 2024 The landlord issued its stage 1 response. It apologised for the delay in responding and said this was due to high demand. In summary, it said: the works were carried out under a qualifying long-term agreement (QLTA) and that it followed the Section 20 process it sent a pre-consultation letter on 27 February 2020 and received responses from residents it sent a second letter on 18 March 2020 and cancelled a planned meeting due to Covid it sent a notice of intention on 14 July 2020 with an estimated cost some leaseholders reported they did not receive the notice and it sent copies again by post and email where possible it checked costs against market rates and the final costs were lower than the estimate it since improved how it manages Section 20 consultations and how it communicates with residents it offered £300 compensation for the delay in responding to the resident’s queries.
13 February 2024 The resident contacted the landlord repeating concerns about poor communication. He said the landlord sent some letters to the wrong address, it delayed some responses and it did not answer some questions. He also said the landlord did not separate the 2 sets of major works or fully address his queries. In summary: Section 20 – scaffolding, electrical, and related works. He said the landlord sent notices late or after it complete the works. He also said he did not receive: a valid Section 20 notice before the works started an opportunity to take part in a consultation or meeting clear details of costs, timing, or contractors Section 20 – fire remedial works.
He said the landlord did not answer questions about costs, removed items without explanation, and did not communicate clearly throughout. He also said he did not receive: a clear Section 20 notice an opportunity to comment on the works clear information on timing 27 February 2024 The landlord confirmed it had escalated the complaint to stage 2 and would respond within 20 working days by 26 March 2024. 21 March 2024 The landlord issued its stage 2 response. It accepted a service failure as it did not address both sets of works at stage 1.
It restated that it sent letters in February 2020, March 2020 and a notice in April 2020, and used QLTA rates to estimate costs. In summary, it said: it still believed it followed the correct process for the 2020 works for the 2021 fire safety works, it sent notices to both the property and contact address, invited comments, and replied to them it had evidence to support this and was still waiting for final costs it apologised for delays and offered £200 at stage 2, in addition to the £300 offered at stage 1.
Referral to the Ombudsman The resident brought his complaint to us, he said: the landlord carried out 2 sets of major works and later billed him without proper involvement he said he did not receive clear information or a chance to discuss the works or costs he said the landlord did not respond to his emails from October 2023 he also said the landlord’s complaint response was general, did not address his points, and did not clearly explain how the process was followed as a resolution, he wants the landlord to admit it did not follow the Section 20 process.
What we found and why The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration. Complaint The landlord’s handling of the Section 20 process for its major works Finding Outside jurisdiction A landlord’s ability to levy a service charge and a leaseholder’s obligation to pay it are governed by the provisions of the lease.
The appropriate body to consider disputes concerning the level or reasonableness of a charge, and/or whether the correct processes were followed, is the First Tier Tribunal (FTT). Leaseholders have the right to apply to the FTT to determine whether a service charge, or a proposed charge, is reasonably incurred and the correct process was followed including the serving of any notices. This can apply whether the charge has already been paid or is still proposed and may relate to completed works or estimated costs.
Complaint The landlord’s response to the resident’s concerns about the major works and its communication Finding Service failure The resident gave us copies of letters dated 6 October 2023 and 9 October 2023. He said he wrote to the landlord on those dates about the 2 major works. He said he sent both letters again by recorded delivery in November 2023 after he did not get a reply. The landlord’s records do not refer to these letters. It is not clear if the landlord received them, or if it received them but did not log them or pass them to the right team.
In its stage 1 response, the landlord explained the Section 20 consultation process and its duties. This explanation was in line with its policy. However, the landlord did not tailor its response to the resident’s concerns. It provided general responses. The resident said he did not receive the notices and asked for clarity about later letters. It would have been reasonable for the landlord to address the resident’s reports that he did not receive the notices and explained what records it held about sending them and confirmed if it sent them to the correct address.
The stage 1 response offered compensation for the delay in replying to the resident’s letters from October 2023 and November 2023. While it recognised a service failure, it was an opportunity for the landlord to address the concerns raised in those letters. There is no evidence it did at the time. The resident escalated the complaint. He said the stage 1 response did not address all of the issues and did not refer to the second set of major works. The landlord did not provide a copy of the notice of intention for the first major works.
The stage 2 response referred to a notice dated 20 April 2020. The stage 1 response referred to notices dated 14 July 2020. A later final accounts letter to the resident on 9 August 2023 referred to a notice dated 14 July 2023. These inconsistent dates caused confusion and reduced the resident’s trust in the landlord’s explanations. The stage 2 response explained the second major works in more detail. It said the landlord sent notices and letters to both the property and the correspondence address.
However, it did not show that it had considered the lease terms on serving notices. In line with the resident’s lease agreement, notices are served properly if served by recorded delivery. Given the resident’s complaint centred on non-receipt of notices, it would have been reasonable for the landlord to review and address whether the method of service complied with the lease obligations. The landlord’s unclear and general replies meant the resident stayed unsure about the major works and had to spend time and trouble chasing for answers.
The different notice dates also caused confusion and reduced the resident’s trust in the landlord’s explanations. Overall, the landlord’s failings relate to poor communication, unclear explanations, and poor record keeping. The landlord did engage with the complaint, gave explanations, and offered some compensation, which shows it did not ignore its obligations. However, its responses lacked clarity, were not tailored to the resident’s concerns, and were not well supported by records.
The landlord offered £450 compensation for its delay in responding to the resident’s enquiries and the failure in addressing both major works in its stage 1 response. While the amount aligns with its compensation policy and our compensation guidance, it did not acknowledge the impact on the resident or fully address the concerns raised. However, as the compensation offered is proportionate to the level of service failure identified, we have not ordered any additional financial redress.
Complaint The handling of the complaint Finding Reasonable redress Our Complaint Handling Code (the Code) sets out when and how a landlord should respond to complaints. The relevant code in this case was the 2022 edition. While the landlord’s interim complaints policy was not in line with the Code at the time, this was accepted due to the landlord experiencing a cyber-attack. However, its current policy now reflects the Code’s timescales of 10 and 20 working days. The landlord operates a 2-stage complaints process.
It says it will acknowledge complaints within 10 working days and aim to respond at stage 1 within 20 working days. It also allows for a peer review at stage 2, which it aims to acknowledge within 10 working days and respond to within 40 working days. The landlord acknowledged the resident’s complaint on 19 January 2024, 4 working days after it was made. It issued its stage 1 response on 2 February 2024, 10 working days after the acknowledgement. This was in line with both its policy and the Code.
The resident escalated the complaint on 13 February 2024. The landlord acknowledged this on 27 February 2024, 10 working days later. It met its policy at the time. The landlord issued its stage 2 response on 21 March 2024, 17 working days after the acknowledgement. This was in line with its policy. The landlord recognised the delay with its response, apologised and offered £50 compensation. Which we consider reasonable. Learning Knowledge information management (record keeping) Clear and complete records support good decisions, create a clear audit trail, and help landlords show how they meet policy and lease requirements.
Communication In this case, unclear and inconsistent responses did not address the resident’s concerns and led to confusion. Clear, tailored communication that responds directly to the issues raised helps build trust and reduces uncertainty. Early, direct engagement helps clarify concerns, reduce confusion, and reach resolution sooner.
This is a structured summary of a published determination. The official decision is the authoritative record. Contains public sector information licensed under the Open Government Licence v3.0.